Contributors: Karolyn Sweeting
Location: Vancouver Island, British Columbia
Land Use: Other
Habitat Type:Watercourse/Riparian
Highlights
Introduction
Objectives
4) To construct a bridge that carried four lanes of traffic on the Inland Island Highway over the Tsable River valley.
5) To build a bridge that was earthquake resistant in a high seismic activity location primarily by reducing the superstructure’s weight.
Process
Actions
PRE-CONSTRUCTION
Prior to the bridge construction, environmental assessments were completed to account for the various plant, animal, and fish species that were distributed throughout the valley. During the approval process, VIHP contracted qualified biologists and consulted with provincial and federal agencies, streamkeepers and conservation groups receiving input from the design of the new highway and bridge structure. This ensured the project complied with government policies and legislation for the protection of the environment.
CONSTRUCTION
Construction of the Tsable River Bridge began on April 25, 1996. Twenty-seven months were allotted for construction. An environmental monitor was employed throughout construction to ensure the contractor was meeting the obligations as specified in Standard Specifications for Highway Construction, Section 195, Protection of the Environment. That person also acted as a resource for construction methods performed in sensitive areas. The Environmental Monitor in turn reported to a VIHP Environmental Coordinator who was responsible for the scope of the project and certified that recommendations matched ministry policy and provided accountability for the project team on environmental issues.
The bridge superstructure was supported by three piers. The exterior piers were constructed with the use of a crane from the roadway and a smaller crane on the valley floor. The construction access to the valley was built at the north bank and included a small temporary bridge to an island. The middle pier was constructed on an island in the river with a small crane on the valley floor. The construction of the middle pier had to be completed during the fisheries window, June 15th to September 15th, when the chance of disturbing the salmonid habitat would be at a minimum. When construction of the middle pier was finished the small bridge and most of the access road was removed. The exposed land was then hydroseeded with a Standard Island Highway Mix.
The bridge superstructure was constructed of concrete cast into single cell box segments. As each segment was cast, it was attached to the previous segment using post-tensioning tendons. This process was repeated alternating from each side of the piers until closure of each span was achieved. This process was referred to as cast-in-place cantilever segmental construction utilizing a traveling form. A total of 137 segments were cast to complete the bridge superstructure.
Transverse ribs were incorporated into the top slab to stiffen the structure and to maximize structural efficiency. Silica fume cement was used throughout the superstructure to provide high strength concrete resulting in the reduction of structural mass and penetration of corrosion caused from water and dissolved deicing chemicals. High density, high quality concrete with an average thickness of 50 millimeters was cast over the top slab as a final wearing surface. The completed structure was 400 meters long, 24 meters wide, and 60 meters above the valley floor.
Results
Construction finished on July 15, 1998 at a cost of $15 million and the bridge was opened to the public on September 25, 1999. The construction of the Tsable River Bridge used 254 construction workers and 150,000 hours of work to complete the project. The Tsable River Bridge was successfully constructed on schedule and under budget.
Next Steps
Acknowledgments
Contacts
Habitat Management
Richard Eliasen
Senior Eng. Technolo
3225 Stephenson Pt. Road
Nanaimo, BC Canada
V9T 1K3
Phone: (250) 756-7278
Email: eliasenr@pac.dfo-mpo.gc.caMinistry of Transportation
Vancouver Island Highway Project
Larry Louis
Bridge Design Coordi
200 – 546 Yates Street
Victoria, BC Canada
V8W 1K8
Phone: (250) 953-4944
Email: Larry.Louis@gems4.gov.bc.ca
Partners
Ministry of Transportation
Vancouver Island Highway Project
Larry Louis
Bridge Design Coordi
200 – 546 Yates Street
Victoria, BC Canada
V8W 1K8
Phone: (250) 953-4944
Email: Larry.Louis@gems4.gov.bc.ca