Contributors: Karolyn Sweeting
Location: , British Columbia
Land Use: Fisheries
Habitat Type:
Highlights
Introduction
Objectives
- Build partnerships with DFO, MELP, HCTF, and non-governmental organizations (Gitanyow Fisheries Authorities and the Steelhead Society of BC);
- Modify existing highway culverts to enable fish passage at the identified culvert related barriers.
- Open productive fish spawning and rearing habitats for steelhead, cutthroat trout and several species of salmon and allow them to recolonize unused habitat;
- Minimize construction impacts on fish and fish habitat while installing new culverts, weirs and riffles.
- Facilitate MoT engineering technicians and contractors to gain valuable expertise in fish passage restoration projects.
Challenges
Process
Actions
In May 1997, the Tea Creek culvert crossings at Highway 37 and Moore Road were assessed for retrofit. The existing culverts were impeding upstream fish migration by a large outlet drop. Stream and culvert assessments were initiated. The water depth in the Highway 37 culvert was less than 30 centimeters and the Moore Road culvert no longer carried water.MoT engineering technicians used a Laser Tech Inc. Impulse 200 range finder to measure the length and slope of the culverts, and used a total station to map and produce site plans. Technical experts, contracted by MELP, visited both culvert crossings on four separate occasions to record spawning and migrations of summer steelhead and cutthroat trout. GFA assisted by using minnow traps to determine fish presence through the placement of traps in suitable locations upstream and downstream of the culverts. Observations by MELP and sampling efforts by GFA showed there were no anadromous fish upstream of these structures. Also, fish were not observed attempting to enter either one of the culverts, suggesting an obstruction of fish passage. In May 1997, the water level dropped considerably at both locations due to low spring runoff.Design
MELP submitted a funding application to HCTF and initiated partnerships in an effort to gather adequate resources to remediate the two culvert crossings. Technical experts at HCTF reviewed the proposals. The Public Advisory Board completed a review and recommended the project for funding. In April 1998, a HCTF Trustee approved a $15,000 contribution to finance the Tea Creek culvert retrofits. The GFA contributed $4,000 and the SSBC committed $2,000 towards the construction costs of this project.
MoT staff designed Tea Creek improvements with recommendations supplied by DFO engineers. The Tea Creek design consisted of re-establishing fish passage at the two identified culvert related barriers by: 1) raising the level of the plunge pool at the Highway 37 culvert and 2) replacing the twin corrugated metal pipe barrier on Moore Road with a 3300 mm bottomless pipearch.
Remediation for the Highway 37 culvert utilized a DFO weir design to reduce the outlet drop. The weir design incorporated tailwater controls that elevated the outlet pool. The design entailed a total of seven weirs, constructed at five to seven meter intervals to facilitate upstream fish migration. Pre-cast concrete lock blocks, in lieu of rock, were notched and used to create the plunge pools. The outlet was armored with riprap to prevent streambed scour. The new bottomless pipearch at Moore Road was installed during a period of low flows in July, 1998 at a 3% gradient.
Results
Initially it was found that the plunge pools at Highway 37 culvert did not seal as leaking occurred between the lock block spaces. In 1999, the high stream velocities from the spring freshet caused the remaining void spaces in the plunge pools to seal with sediment. Late summer observations at the Highway 37 site indicated that successful spawning and rearing areas have resulted from the re-construction of the weirs.
The Moore Road culvert provided an unrestricted passage for fish by minimizing impacts to the natural channel by retaining the natural streambed and stream width.
Ongoing performance monitoring for Tea Creek was undertaken by DFO, MELP, MoT and GFA to evaluate the lock block weir system and the bottomless pipearch design. Photo points and on-site visits were used to compare the success of this project with pre-construction observations. The Creek was monitored for fish passage and structural stability. The GFA contributed to the long-term monitoring of fish passage (summer steelhead, cutthroat trout, and coho salmon) during their respective migration periods. They conducted creekwalks to determine which species and populations were using the new habitat and monitored for potential stream obstructions, such as beaver dams, to ensure that they did not create problems for fish migration. Juvenile sampling upstream and downstream of both culvert sites indicated an abundance of salmonid species. Fish passage was no longer a problem at this site and seven kilometers of habitat was re-opened in Tea Creek.
The Tea Creek project was completed under-budget and as a result, the surplus funds from HCTF, MELP, and SSBC were used for the culvert retrofit at John Brown Creek.
John Brown Creek
Problem
The culvert at John Brown Creek was assessed for fish presence upstream and downstream. Site studies indicated that many small but productive streams were alienated from fish production due an obstruction from a one-meter outlet drop and high culvert velocity. On-site inspections were conducted by a joint DFO, MELP, and MoT team to see that if the culvert was retrofitted, eight kilometers of unused habitat would be opened up to fish. MoT developed a plan for culvert retrofit and instream work.
Design
A “Newberry Riffle” design was used for the weirs to create a ‘natural’ pool and riffle sequence at the outlet. These rock riffles functioned to create two pools, that would recruit gravel, aerate water and assist in fish passage. The average pool-riffle spacing was six bank full widths.
Results/Monitoring
A two-phase approach was taken for John Brown Creek: 1) baffles were implemented for juvenile fish passage; and 2) backwatering was done for all fish access. The baffle installation was a MoT design that was retrofitted to the culvert to slow water velocity, to provide rest areas for fish, to promote gravel recruitment, and to trap sediments. In summer 2000, works were undertaken to construct a tailwater pool and riffles to backwater the culvert and to facilitate upstream fish passage. The ‘natural’ rock riffles for retrofitting the 2.2-meter multiplates completed the necessary backwatering. Riprap was placed downstream of the culvert outlets to minimize the height of the culvert from the stream.
Post-remediation monitoring was conducted during the spring freshet in 2001 to ensure that the new eight-kilometer open channel was used by summer steelhead, cutthroat trout, coho, and pink salmon. Also that productive fish spawning and rearing habitat were accessible. Since completion, competition was observed between Dolly Varden char and bulltrout resident fish species, upstream of the culvert.
Results
Next Steps
Contacts
Rod Silver
Manager, HCTF and Sp
780 Blanshard Street
Victoria, BC Canada
V0J 2N0
Phone: (250) 356-6124
Email: Rod.Silver@gems2.gov.bc.caMinistry of Transportation
Bulkley Lakes District Office
Fred Seychuk
3793 Alfred Ave.
Smithers, BC Canada
V0J 2N0
Phone: (250) 847-7731
Email: Fred.Seychuk@gems7.gov.bc.caMinistry of Environment, Lands and Parks
Fish, Wildlife and Habitat
Dana Atagi
Fisheries Section He
2nd Fl. 3726 Alfred Ave.
Smithers, BC Canada
V0J 2N0
Phone: (250) 847-7290
Email: datagi@smithers.env.gov.bc.caGitanyow Fisheries
P.O.Box 148
Kitwanga, BC Canada
V0J 2A0
Phone: (250) 849-5373The Steelhead Society of BC
#103-131 Water Street
Vancouver, BC Canada
V6B 4M3
Phone: (604) 684-6242
Fax: (604) 684-4745
Partners
Habitat Conservation Trust Fund
Rod Silver
Manager, HCTF and Sp
780 Blanshard St.
Victoria, BC Canada
V8W 2H1
Phone: (250) 356-6124
Email: Rod.Silver@gems2.gov.bc.ca
Ministry of Transportation and Highways
Bulkley Lakes District Office
Fred Seychuk
Survey Crew
3793 Alfred Ave.
Smithers, BC Canada
V0J 2N0
Phone: (250) 847-7731
Email: Fred. Seychuk@gems7.gov.bc.ca
Ministry of Environment, Lands and Parks
Fish, Wildlife and Habitat
Dana Atagi
Fisheries Section He
2nd Fl. 3726 Alfred Ave.
Smithers, BC Canada
V0J 2N0
Phone: (250) 847-7290
Email: dana.atagi@gems3.gov.bc.ca